The Safety, Health and Welfare at Work (Construction) Regulations 2013 set the duties of clients, designers, project supervisors and contractors on construction projects in Ireland. A client must appoint a Project Supervisor for the Design Process (PSDP) and a Project Supervisor for the Construction Stage (PSCS) where the work involves a particular risk, where more than one contractor is involved, or where the project is large enough to be notified to the Health and Safety Authority (HSA). Notification is required where construction work is planned to last longer than 30 working days or the volume of work is scheduled to exceed 500 person days.

This guide covers those thresholds, the safety and health plan, and what the Regulations ask of contractors. It describes S.I. No. 291 of 2013 as read on 26 November 2026. The Regulations were amended in 2019, 2020 and 2021, so check the current text before relying on a detail. It also says plainly what the Irish edition of Featherstone Safety Hub does and does not include for construction.

General information, not legal advice. Not reviewed by an Irish solicitor.

Key points

  • The Regulations came into operation on 1 August 2013 and apply to construction work.
  • The duty to appoint a PSDP and PSCS in writing applies where the work involves a particular risk, more than one contractor is involved, or the notification threshold is met (Regulation 6). It does not apply to every project.
  • The HSA must be notified where work is planned to last longer than 30 working days or to exceed 500 person days: by the client (Regulation 10, form AF1) and by the PSCS before work begins (Regulation 22, form AF2).
  • Where notification is not required, a safety and health plan is required only where the work involves a particular risk (Regulation 12(2)).
  • Contractors must co-operate with the PSCS, follow the safety and health plan, and provide relevant extracts from their Safety Statement (Regulation 24).
  • On its Construction plan, the Irish edition of Featherstone Safety Hub records projects under these Regulations. It does not notify the HSA or submit AF1 or AF2 for you.

What are the Construction Regulations 2013?

They are regulations made under the Safety, Health and Welfare at Work Act 2005, with the citation S.I. No. 291 of 2013. They sit on top of the Act: a construction employer still has every general duty in the 2005 Act, including a written risk assessment and a Safety Statement, and the Construction Regulations add project-level duties.

Terms used in this guide

  • Client. A person for whom a project is carried out.
  • Project. An activity which includes or is intended to include construction work.
  • Contractor. A contractor or an employer whose employees undertake, carry out or manage construction work, or a person who carries out or manages construction work for a fixed or other sum and supplies materials, labour or both.
  • Project supervisor. An individual or body corporate appointed under Regulation 6(1): the PSDP for the design process and the PSCS for the construction stage.
  • Safety and health plan. A plan in writing prepared and developed under Regulations 12 and 16.
  • Safety file. A file prepared under Regulations 13 and 21, containing safety and health information to be taken into account during any later construction work on the structure.

What are a client's duties?

HSA guidance summarises a client's duties under the Regulations as follows. The HSA says they are intended to ensure that the project is designed and constructed by competent persons.

  • Employ competent designers and contractors to carry out the work.
  • Appoint in writing, before design work starts, a competent and adequately resourced PSDP, as required.
  • Appoint in writing, before construction work starts, a competent and adequately resourced PSCS, as required.
  • Co-operate with the project supervisor and supply necessary information.
  • Keep and make available the safety file for the completed structure.
  • Provide a copy of the safety and health plan prepared by the PSDP to every person tendering for the project.
  • Notify the Authority where construction is likely to take more than 500 person days or 30 working days.

The words "as required" matter. The sections below set out what the law requires and when, regulation by regulation. The HSA also publishes a guide for homeowners: it says the Regulations apply to construction work a homeowner pays to have done in their home, and not to do-it-yourself jobs.

Good practice for any client, whether or not a project supervisor has to be appointed, is to ask each contractor for the relevant parts of their Safety Statement and their method statement before work starts, and to keep a note of what was received and when.

When must a client appoint a PSDP and a PSCS?

Regulation 6(1) says a client must appoint, in writing, a competent project supervisor for the design process and a competent project supervisor for the construction stage, and must obtain written confirmation that each has accepted. Regulation 6(5) then limits when that applies. Paragraph (1) does not apply unless:

  • the work involves a particular risk, including but not limited to a risk referred to in Schedule 1, or
  • more than one contractor is involved, or
  • Regulation 10 applies, meaning the project meets the notification threshold.

So the appointment duty is not universal. A small job with a single contractor, no particular risk and a short duration falls outside it. Many projects do meet one of the three conditions, most often because more than one contractor is on the job.

Appointing project supervisors (Regulation 6)
QuestionWhat the Regulation says
When is the PSDP appointed?At or before the start of the design process
When is the PSCS appointed?Before commencement of the construction work
Can the client appoint themselves?Yes, if competent to undertake the duties involved
Can one person or company hold both roles?Yes, if competent to undertake the duties involved
What must the client check first?Regulation 7: that the appointee has allocated or will allocate adequate resources to perform the duties

Under Regulation 24(2), a contractor who is not aware that project supervisors have been appointed must promptly inform the client of the client's duties under Regulation 6.

What counts as a particular risk?

Schedule 1 is a non-exhaustive list of work involving particular risks to the safety, health and welfare of persons at work. The words "including but not limited to" in Regulation 6(5) mean other work can qualify too.

  1. Work which puts persons at risk of falling from a height, burial under earthfalls or engulfment in swampland, where the risk is particularly aggravated by the nature of the work, the processes used or the environment.
  2. Work which puts persons at risk from chemical or biological substances constituting a particular danger, or involving a statutory requirement for health monitoring.
  3. Work with ionising radiation requiring the designation of controlled or supervised areas.
  4. Work near high voltage power lines.
  5. Work exposing persons to the risk of drowning.
  6. Work on wells, underground earthworks and tunnels.
  7. Work carried out by divers having a system of air supply.
  8. Work carried out in a caisson with a compressed-air atmosphere.
  9. Work involving the use of explosives.
  10. Work involving the assembly or dismantling of heavy prefabricated components.

When must the HSA be notified of a construction project?

The threshold is the same in both notification duties: construction work "planned to last longer than 30 working days or the volume of work is scheduled to exceed 500 person days". Either limb is enough.

Notifying the HSA of a construction project
WhoRegulationWhat and whenForm
The client10Promptly give notice in writing, in an approved form, of the particulars known about the project supervisor appointmentsAF1
The PSCS22Before the work begins, give written notice promptly with the particulars listed in Schedule 3, and display those particulars clearly on the construction site, updated if necessaryAF2

Person days are the days worked by everyone on the job added together. As an illustration, 30 people working for 20 working days is 600 person days, so that job is notifiable even though it lasts fewer than 30 working days. Two people working for 40 working days is only 80 person days, but that job is notifiable because it lasts longer than 30 working days.

When is a safety and health plan required, and what goes in it?

The plan is started by the PSDP and developed by the PSCS. Under Regulation 12(1) the PSDP prepares a written safety and health plan on a preliminary basis, specifying among other things a general description of the project and the time within which it is intended to be completed, information on other work activities on the site, work involving particular risks, and the conclusions drawn by designers and the PSDP as regards the general principles of prevention.

Regulation 12(2) limits the requirement: "Where notification is not required under Regulation 10, a safety and health plan is required only for sites where the work concerned involves a particular risk, including but not limited to any of those referred to in Schedule 1."

Under Regulation 16 the PSCS must further develop the plan before construction work starts, adjust it as the work progresses, include specific measures for work involving a particular risk, include rules for the execution of the construction work, and make sure the plan and its rules are in writing and brought to the attention of all contractors and other relevant persons who may be affected.

Is a safety and health plan required?
ProjectPlan required?
Notifiable to the HSA (over 30 working days or 500 person days)Yes
Not notifiable, but involves a particular riskYes
Not notifiable and no particular riskNot required by Regulation 12. The contractor's own risk assessment and Safety Statement under the 2005 Act still apply

What must contractors do?

Regulation 24 lists the general duties of a contractor. In summary, a contractor must:

  • co-operate with the PSCS so that the project supervisor can comply with the law
  • promptly provide the PSCS with site-specific information likely to affect anyone's safety, health or welfare or that might justify a review of the safety and health plan, including any relevant extract from the contractor's Safety Statement
  • provide the PSCS with information about any accident or dangerous occurrence the contractor has to report, and a copy of the report
  • promptly provide, in writing, the information needed to prepare the safety file
  • comply with directions from the project supervisors
  • bring the rules in the safety and health plan to the attention of the contractor's employees, comply with the plan, and ensure so far as is reasonably practicable that employees comply with it
  • apply the general principles of prevention in a consistent manner.

Cards, induction and safety officers

As made in 2013, Regulation 25 requires every contractor, or other person under whose direct control people work on a construction site, to make sure each worker holds a valid safety awareness registration card where the Regulations require one (the Safe Pass scheme is named in Schedule 4), holds the appropriate construction skills registration card for the tasks listed in Schedule 5, and has received site-specific safety induction where required. On the day a worker first starts on site, the contractor must ask to see the card and give the PSCS written confirmation.

Regulation 26 requires a contractor who normally has more than 20 persons under direct control on a construction site at any one time, or 30 persons engaged in construction work, to appoint in writing one or more competent persons as safety officers. Regulation 23 requires the PSCS to facilitate the appointment of a site safety representative where more than 20 persons are normally employed at any one time on a construction site.

What is the safety file, and who keeps it?

The PSDP prepares a written safety file appropriate to the characteristics of the project, containing relevant safety and health information to be taken into account during any subsequent construction work, and promptly delivers it to the client on completion (Regulation 13). The PSCS co-ordinates the contractors so that the information needed for it is provided in writing (Regulation 21).

The client must keep the safety file available for inspection by anyone who may need the information for later construction work on the structure or to meet their own duties (Regulation 8). When the client disposes of their interest in the structure, delivering the safety file to the person who acquires it is sufficient compliance, and that person must then keep it available.

Which duties apply? A worked example

This example is illustrative. It is not a real project.

A retailer plans to refit a shop unit. A main contractor will run the job, with an electrical subcontractor and a shopfitting subcontractor. The programme is 20 working days with about eight people on site, so roughly 160 person days. Some work will be done from a mobile tower over the stairwell.

Working through the thresholds
QuestionAnswer for this projectResult
More than one contractor?Yes: threeThe client must appoint a PSDP and a PSCS in writing (Regulation 6)
Longer than 30 working days, or over 500 person days?No: 20 working days and about 160 person daysNo AF1 or AF2 notification to the HSA
A particular risk?The client and designers judge the stairwell work to carry an aggravated risk of falling from a heightA safety and health plan is required (Regulation 12(2))
Contractor duties?Each contractor gives the PSCS relevant Safety Statement extracts, follows the plan and checks cards on day oneRegulations 24 and 25

If the programme slipped to 35 working days, the project would cross the notification threshold and the client and the PSCS would each have a notification duty. Whether work involves a particular risk is a judgement on the facts of the job. If in doubt, treat it as one or take advice.

Does Featherstone Safety Hub cover construction in Ireland?

Yes, on its Construction plan, and it is better to be clear about what that covers. The Construction plan in the Irish edition records projects under these Regulations: the client, PSDP and PSCS, a check of the tests in this guide, a record of when AF1 and AF2 were sent, the safety and health plan, project documents including the safety file, and site inspections. It does not notify the HSA or submit any form for you, and it is not the same as the construction tools in the United Kingdom edition.

The Irish Construction plan and construction work
The Construction plan includesThe Construction plan does not include
Construction projects with the client, PSDP and PSCS on record, and their written appointments in the project's document registerNo AF1, AF2 or IR1 forms sent, and no notification of any kind to the HSA
A check of the notification threshold (Regulations 10 and 22), the appointment conditions (Regulation 6(5)), the safety and health plan rule (Regulation 12(2)) and the site safety representative test (Regulation 23)No decision on whether work involves a particular risk: that judgement stays with you
A record of when AF1 and AF2 were sentNo RAMS builder, and no drafting of method statements
A safety and health plan with draft, review, approval, issue, revisions and PDF exportNo site inductions, and no register of Safe Pass or construction skills cards
A project document register with Irish categories, including the safety fileNo subcontractor portal, plant and equipment register, project permits or toolbox talks
Site inspections and corrective actions, plus everything in the Complete plan: risk assessments, accident records with an HSA reporting decision, the contractor register, permits to work and training recordsNo training courses

The other Irish plans do not include construction projects. A contractor on those plans can still use the Hub for the general duties every employer has under the 2005 Act. Whichever plan you use, the duties in this guide stay with the client, the project supervisors and the contractors.

Frequently asked questions

What do PSDP and PSCS stand for?

Project Supervisor for the Design Process and Project Supervisor for the Construction Stage. Both are appointed in writing by the client under Regulation 6 of the Construction Regulations 2013, where that Regulation applies.

Does every construction project need a PSDP and a PSCS?

No. Under Regulation 6(5) the duty to appoint applies where the work involves a particular risk, where more than one contractor is involved, or where the project must be notified to the HSA.

When does a construction project have to be notified to the HSA?

Where the construction work is planned to last longer than 30 working days or the volume of work is scheduled to exceed 500 person days. The client notifies under Regulation 10 (form AF1) and the PSCS notifies before work begins under Regulation 22 (form AF2).

Is a safety and health plan always required?

No. Where notification to the HSA is not required, Regulation 12(2) says a safety and health plan is required only for sites where the work involves a particular risk, including but not limited to those in Schedule 1.

Can a client act as their own project supervisor?

Yes, if competent to undertake the duties involved. Regulation 6(2) also allows one individual or body corporate to be appointed for both the design process and the construction stage if competent.

Does a contractor still need a Safety Statement?

Yes. The Construction Regulations add to the 2005 Act and do not replace it. Regulation 24 requires contractors to give the PSCS relevant extracts from the Safety Statement prepared under section 20 of the Act.

Does Featherstone Safety Hub have a construction module in Ireland?

Yes, on the Construction plan. It records projects with the client, PSDP and PSCS, checks the tests in these Regulations, records when AF1 and AF2 were sent, and keeps the safety and health plan, project documents and site inspections. It does not send forms to the HSA, and it does not include RAMS, site inductions or a subcontractor portal in Ireland.

Sources

This guide is general information about Irish health and safety law and Health and Safety Authority guidance, written for employers. It is not legal advice, it has not been reviewed by an Irish solicitor, and it is not published or endorsed by the Health and Safety Authority. Acts and regulations are amended from time to time: check the current legislation at irishstatutebook.ie and take advice on your own situation.